@StateDept’s “New Camp Sullivan” in Afghanistan Four Years On: A Lovely $103.2 Million Flat Dirt

Help Fund the Blog |  Countdown:  6 Days to Go

______________________________________

 

 

State/OIG’s Office of Evaluation and Special Projects has released its Evaluation of the Bureau of Diplomatic Security’s Aegis Construction Contract at Camp Eggers in Afghanistan (PDF). Well, nothing good to read in this report, but the flat dirt is lovely, and makes us want to pull our hair out in  frustration. We bring you some GIFs to make us all feel better.

Camp Eggers Afghanistan, Photo by State/OIG

Things of note excerpted from the IG report:
The Department awarded Task Order 10 in July 2011 to Aegis (GardaWorld)  to provide and manage an armed and unarmed guard force known as the Kabul Embassy Security Force (KESF) for Embassy Kabul and other U.S. diplomatic facilities within Kabul, Afghanistan. On September 30, 2014, the Department modified Task Order 10 held by Aegis to allow for the renovation of Camp Eggers in its entirety and to erect a new facility known as the “New Camp Sullivan.” […]Modification 43 was issued to Aegis under a firm fixed price for the design-build of the Camp Eggers construction project. The task order modification was valued at about $173.2 million with an estimated completion date of March 31, 2016.
[…] An Aegis official told OIG he did not believe the company had undertaken any construction projects other than building a shooting range at Camp Sullivan. An OBO official noted that Aegis lacked the “institutional expertise” to build to OBO standards, and several Department officials told OIG that they had doubts about Aegis’s ability to carry out major construction work.

 

On January 10, 2014, AQM awarded a contract to the management consulting firm, Markon, on behalf of DS to perform professional engineering services.[..] Markon […] warned the Department in August 2014—a month before the task order was modified—that the project would not likely be finished on time or on budget. The Department nonetheless chose to move forward with this fundamentally unsuitable construction mechanism because of what it viewed as exigent need and a lack of alternatives.

 

Multiple Department officials, as well as an Aegis official, told OIG that they viewed the initial 18-month project timeline as unreasonable. An official from AQM expressed skepticism that such an extensive project could ever be completed so quickly in a construction environment as logistically complex as Afghanistan.[…]The renovation of Camp Eggers entailed extensive demolition and redevelopment, including [snip] the construction of new facilities. The “New Camp Sullivan” facility was intended to become a self-supporting, multi-use facility, which included life support for up to 900 personnel (expandable to house up to 1,500 personnel) all within a secure perimeter.

 

Aegis, through its subcontractor, CWI, purchased materials costing approximately $19.4 million for Camp Eggers. However, roughly 23 percent of these materials ($4.5 million) were obtained without submitting proper documentation or receiving proper Department approval.[…]The materials had to be stored due to numerous project delays, which prevented CWI from using the materials as they were delivered. The storage continued throughout the life of the contract until all of the materials were disposed of by May 2018. Over the life of the task order, the Department wasted about $22 million on materials that were never used and then paid to store them

 

Although Aegis continuously missed project milestones and failed to adhere to contract requirements, the Department still did not take meaningful corrective action against Aegis beyond issuing LOCs. As noted, these were primarily issued by DS. The Department also held a number of meetings with Aegis personnel to discuss the lack of progress made on the project, but no further corrective action was taken.

 

The Department reached a settlement with Aegis in March 2019 whereby the Department agreed to pay Aegis a total of $94.6 million. Based on this figure, in addition to three separate contracts with Markon Solutions, Incorporated for professional engineering and design review services, OIG identified a total of $103.2 million in questioned costs related to the Camp Eggers project.[…] the “New Camp Sullivan” remained flat dirt after more than four years of effort. The Department estimated that approximately 10 percent of the construction work was completed, and the 100 percent design—the final design—remained unfinished.

After the termination of the Camp Eggers project, the Department transferred materials stored in Kabul to fill other U.S. Government needs in the area. Regarding the materials in Dubai, Red Sea Housing Services Company FZE (Red Sea), the company with whom the Department ordered CHUs, reached a final termination settlement valued at about $2.5 million with Aegis and the Department under which Red Sea would keep all the materials and equipment they procured on behalf of the Department. The remaining materials in Sterling, VA were disposed of through the General Services Administration’s excess property program and some were scrapped.

Via reactiongif.com

 

OIG’s conclusion: [T]he Department’s sense of urgency, the selection of a non-construction contractor, the assignment of officials inexperienced in construction to oversee the project, and the failure to hold the contractor accountable for particular instances of poor performance led to the expenditure of more than $100 million without any discernible benefit to the Department or the people it intended to protect. OIG also notes that, more generally, this project illustrates many of the broader concerns that arise when the Department pursues construction projects in contingency or otherwise challenging environments. The Camp Eggers project again highlights the importance of making well-informed, thoughtful choices regarding the most appropriate contract vehicle; careful, consistent oversight; and development of a process for construction work in contingency zones that is sufficiently nimble to address urgent security needs but also considers the resources and capabilities of all relevant Department bureaus.