We have previously written about the State Department’s Foreign Affairs Security Training Center (FASTC) project that has been snared in a tug of war in Congress.
- A Look at the DOS Foreign Affairs Security Training Center (FASTC) in Fort Pickett and Nottoway County
- Final Environmental Impact Statement (EIS) For Foreign Affairs Security Training Center (Fort Pickett) Now Available
- Elected Officials Applaud Land Purchase For State Dept Fort Picket Training Facility
- FASTC Hard Skills Training Center: “Who owes who favors?”
- Uh-oh Dept: Royce Issues Subpoena to OMB Over Diplomatic Security Training Facility Documents
- GAO: State Dept Management of Security Training May Increase Risk to U.S. Personnel
- Hard Skills Training Center at Old Smelting Plant Site?
On September 9, the Government Accountability Office finally released its review of the project. Concerned by the considerable variation in the cost estimates for FASTC and FLETC, members of Congress requested that GAO provide further information on both the requirements and costs of DS training. GAO examined (1) key site requirements critical to the provision of DS training and the extent to which the FASTC and FLETC proposals meet these requirements and (2) the estimated capital and recurring costs of these proposals and the extent to which the capital cost estimates conform to leading practices for reliable cost estimates. The GAO report was publicly released on September 16.
See Figure 3: Key Events in Plans to Consolidate Bureau of Diplomatic Security Training (pdf)
Excerpt below:
State has been in the process of looking for a site suitable for its DS training facility for more than a decade. In 2011, State and the General Services Administration (GSA) identified Fort Pickett near Blackstone, Virginia, as the preferred site for the Foreign Affairs Security Training Center (FASTC). The initial 2012 master plan for FASTC would have consolidated hard- and soft-skills training at Fort Pickett for an estimated cost of $925 million. In March 2013, State reduced the scope of FASTC to exclude facilities for soft-skills training and life support functions, such as dormitories and a cafeteria, ultimately decreasing the estimated cost of the current proposal to $413 million. Also in 2013, the Office of Management and Budget (OMB) directed State to work with the Department of Homeland Security (DHS) to assess the viability of using the Federal Law Enforcement Training Centers (FLETC) in Glynco, Georgia, to accommodate DS’s training. In November 2013, FLETC submitted a business case to OMB indicating that it could meet DS’s requirements, including soft-skills training, for an estimated cost of $272 million. Following this assessment, DS, FLETC, and OMB could not agree on a path forward.
In April 2014, the administration reaffirmed the selection of Fort Pickett for FASTC, and State and GSA began implementing their plan to construct FASTC. State and GSA have obligated about $71 million to date toward FASTC at Fort Pickett.2 In May 2015, GSA purchased land and, in June 2015, awarded a contract for the initial phase of construction of FASTC.
[…]
[W]e analyzed four of DS’s requirements that we determined were critical in the selection of a site for DS’s training facility and found that Fort Pickett fully met all four while FLETC did not fully meet any.7 First, building FASTC at Fort Pickett would enable DS to consolidate at one location 10 of the 12 widely scattered hard-skills training venues it is currently using.8 FLETC can accommodate many of these venues on its Glynco campus but would have to conduct some exercises at a Marine Corps training facility about 30 miles away. Second, we found that Fort Pickett is available for nighttime training, which DS conducts on about 190 days per year, while at FLETC there may be some limitations on nighttime training. We also determined that the Fort Pickett site held advantages in terms of proximity to Washington, D.C., and exclusivity of use, both of which were requirements highlighted in reports stemming from the Benghazi ARB.
We found that neither the FASTC nor the FLETC estimate for capital costs fully meets best practices. The FASTC estimate fully or substantially meets three of the four characteristics—comprehensive, well documented, and accurate—and partially meets one characteristic of reliable cost estimates— credible; the FLETC estimate partially or minimally meets all four characteristics.10 FLETC officials noted that their estimate was prepared in a short period of time based on incomplete information regarding State’s requirements; more complete information would have enabled them to develop a more comprehensive estimate. See enclosure V for more detail on our assessment. Our assessment of the reliability of these cost estimates focused on the processes used to develop the estimates rather than estimates themselves, enabling us to make a more direct comparison of their reliability.
In addition to capital costs for acquisition and construction of a DS training center, the government will incur costs of sending students to training. These recurring student costs include travel, lodging, meals and incidental expenses, and compensation for time spent traveling. We projected these costs over 10, 25, and 50 years in three different scenarios for both the FASTC and FLETC proposals. We estimate that the costs of sending students to FASTC over 10 years will be $43 million to $121 million less, in net present value, than sending students to FLETC.11 The difference in student costs between FASTC and FLETC increases over time, from between $122 million and $323 million less for FASTC after 25 years, to between $309 and $736 million after 50 years. See enclosure III for further details on the assumptions used in each of these scenarios.
Click on 672362 to read the full report (38 pages – pdf).
Maybe this is the end of it and the project at Fort Pickett can finally go forward? It is likely that there will be at least one more hearing on this, one congressional committee (was that HOGR?) promised a hearings once the GAO report is completed.
#