U.S. Embassy Kabul Construction Cost: From $625.4M to $792.9M, and Going Up, Up and Away

Posted: 12:55 am EDT
[twitter-follow screen_name=’Diplopundit’ ]

The Government Accountability Office (GAO) recently released its report on Embassy Kabul Construction. Below is a a quick summary:

Since re-opening in 2002, the U.S. embassy in Kabul, Afghanistan, has experienced a dramatic increase in staffing, followed by a gradual drawdown. State has invested or plans to invest a total of $2.17 billion in U.S. facilities to address current and projected space needs. State awarded two contracts in 2009 and 2010 to construct additional on-compound housing and office facilities. State partially terminated one contract for the convenience of the U.S. government, and expanded the construction requirements of the second, affecting cost and schedule.

Schedule and cost: The Embassy Kabul project was originally scheduled for completion last summer but is now projected to be completed in fall of 2017. The cost has also increased from $625.4 million to $792.9 million.

Where two is better than one: Instead of building one temporary vehicle maintenance facility, the State Department ended up  funding two new, temporary vehicle maintenance facilities—one at Camp Sullivan (built by OBO) and one at Qasemi Lot (to be built by DS). Apparently, post officials reported that there are security concerns with using the Sullivan vehicle maintenance facility. And if that’s the case, one wonders why OBO did not scrub the other one, hey?

Which five overseas posts have hardened trailers? According to DS officials, hardened trailers could be required as part of State’s containerized housing and office unit task orders. State reported to the GAO that the hardened trailer specification has been applied to temporary facilities at five overseas posts.

Temporary facilities: As of February 2015, temporary facilities on the embassy compound provided nearly 1,100 desks and 760 beds.

Permanent facilities: Once the current construction is completed, the Kabul embassy’s permanent facilities—both older and newly constructed office and apartment buildings—will contain 1,487 desks and 819 beds. Those totals do not include the desks or beds in temporary offices and housing facilities.

The never ending story: State planning documents, as well as post and OBO officials, identify a continued need for some of the temporary facilities following completion of the permanent facilities in 2017. That would be 875 temporary desks and 472 to 640 temporary beds.  The GAO notes that even with the permanent construction completion “temporary housing will continue to provide between 37 and 44 percent of the available beds on-compound” at Embassy Kabul.

Image via gao.gov

Image via gao.gov

What the GAO found:

  • Cost and schedule have increased for the Kabul embassy construction project, in part due to incomplete cost and risk assessment. Cost for the 2009 and 2010 contracts has increased by about 27 percent, from $625.4 million to $792.9 million, and is likely to increase further. Projected completion has been delayed over 3 years to fall 2017. The Department of State (State) did not follow its cost containment and risk assessment policies, resulting in lost opportunities to mitigate risks. These risks, such as delays in the sequencing of the two contracts, eventually materialized, increasing cost and extending schedule. Unless State follows its policy, it may be unable to avoid or mitigate risks to cost and schedule on future projects.
  • Since 2002, State has built over $100 million in temporary buildings (intended for no more than 5 years’ use) to meet space needs on-compound but has no security standards tailored to those facilities. On completing the project in 2017, all temporary facilities will be 5 to 10 years old, and their continued use is likely.
  • State does not have a strategic facilities plan for Kabul that documents current and future embassy needs, comprehensively outlines existing facilities, analyzes gaps, provides projected costs, and documents decisions made. Lack of such a plan has inhibited coordination and undermined the continuity necessary to address emergent needs at the Kabul embassy.

Too many cooks and constant personnel turnover:

According to State officials in Kabul and Washington, coordination to address the Kabul embassy’s future needs is particularly difficult due to the large number of stakeholders in Kabul and in Washington. Additionally, the constant personnel turnover caused by the 1-year tours served by most management, facilities, and security staff in Kabul results in lack of continuity in decision making. As far back as January 2006, the State Office of Inspector General also identified “the near total lack of institutional memory” stemming from the lack of staff continuity and a “never-ending” learning curve as the most serious impediment to good executive direction at the U.S. embassy in Kabul.

Post and Inter-Bureau Cooperation: Embassy Kabul, DS, OBO

Without a comprehensive plan that provides a strategic framework to document mission needs, catalog existing facilities, analyze gaps, provide projected costs, and document recommendations, the competing proposals of the post’s many stakeholders are difficult to manage, prioritize, and reconcile. As a result, State officials in Kabul said that these meetings suffer from no common vision and a lack of decision making. Consequently, State has been challenged to efficiently address changing embassy needs in several instances on- and off-compound. For example:

      • Interference with on-compound construction—OBO officials in Kabul expressed frustration that proposals for new projects would often conflict with plans previously agreed to by previous post management staff. For example, during our fieldwork, post management proposed to locate a helicopter landing zone near the embassy warehouse. However, according to OBO officials on-site, they had arranged with the previous management team to reserve that space as a staging area for the contractor to build the warehouse expansion. When asked about this, post management officials stated that they had no continuity document that informed them of this earlier decision.
      • On-compound physical security upgrades—DS first requested changes to the embassy compound’s security perimeter in December 2010 and added more requirements in response to attacks against the compound in September 2011. In February 2013, the post urged OBO to provide a project schedule and expedite the upgrades. However, that was not done and as of March 2015 OBO and DS had not reached agreement on schedules and costs for some security upgrade projects.
      • Camp Seitz—In 2013, DS and post management decided to relocate the Kabul Embassy Guard Force from Camp Sullivan and the Protective Security Detail (movement protection) Guard forces from another camp to sites closer to the embassy compound due to security concerns. To facilitate this, DS initiated the acquisition of the Camp Seitz site through OBO. However, according to State officials, DS then began construction of temporary housing at Camp Seitz without submitting the design to OBO for review or applying for a building permit. After OBO became aware of the completed construction, it identified fire safety deficiencies that DS had to correct.
      • Camp Sullivan, Camp Eggers, Qasemi Lot Vehicle Maintenance Facility—As part of the security contractor relocation, post management and DS proposed removing several support facilities, including a vehicle maintenance facility, from an ongoing construction project at Camp Sullivan and transferring them to Camp Eggers. Post management and DS officials stated that once the temporary vehicle maintenance facility on-compound is demolished to make way for apartment buildings 2 and 3, it would be better for security and logistics to build the replacement vehicle maintenance facility close to the compound rather than at Camp Sullivan. However, OBO proceeded to build the Sullivan vehicle maintenance facility because negotiations for the 30 leases required at Camp Eggers were not complete, and OBO was concerned that if an alternative vehicle maintenance facility was not in place, construction of apartments 2 and 3 could be delayed and their costs increased.56 Discussions continued among OBO, DS, and post management, and the proposed vehicle maintenance facility was shifted to Qasemi Lot, a site adjacent to Camp Seitz. OBO decided not to descope the Camp Sullivan vehicle maintenance facility until plans for a replacement facility at Qasemi Lot were approved by OBO and DS had awarded a construction contract with a scheduled completion date prior to the demolition date for the existing vehicle maintenance facility on- compound. As a result, State is funding two new, temporary vehicle maintenance facilities—one at Camp Sullivan (built by OBO) and one at Qasemi Lot (to be built by DS).57

 #